Client: Gloucestershire County Council
Consultant: Halcrow
Main Contractor: Norwest Holst
Anchor Installer: Smith’s (Gloucester) Ltd
A stream feeding the Gloucester and Sharpness Ship Canal needed to be redirected as part of the
overall construction of the by-pass. A new channel was cut and erosion protection measures were
required.
Several layers of material were used to create a water tight base in the channel. S6 Geo anchors were
installed and proof tested to 5kN, using hand held equipment, to secure Maccaferri MacMatR in
position and provide an easily installed erosion protection scheme. The redirected section of the river
was then linked up with the Ship Canal.
|
Anchor System: S06EA aluminium alloy anchor c/w 2m of 4mm Ø stainless steel wire tendon, 92mm Ø polyethylene load plate & 4mm recessed wedge grip. |
||
|
Quantity: 72 |
Anchor Design Life: 20 yrs |
Soil Type: Clay overlying sand |
Featured Case Studies
-
A1 (m) Bramham To Wetherby Upgrade Scheme, Paradise Farm
View Case Study
-
Banks Wood, Dowpits Lane Appleby-in-Westmorland, Cumbria
View Case Study
-
Burgess Hill Embankment Strengthening
View Case Study
-
Power Line Crossing, Glasgow
View Case Study
-
White Lion Close, Summerhill, Wrexham
View Case Study
-
Wickham Market Bridge, Suffolk
View Case Study